May 4, 2018
Below you will find our weekly construction 3-week look-ahead schedule to help you plan around const
ruction. These will be updated bi-weekly. I am always happy to hear from residents and merchants with suggestions for improvements and any concerns you may have.
San Francisco Public Works
Dadisi Najib, Public Relations Officer
Phone: 415-748-7562 (cell) *urgent issues only please
Email: Dadisi Najib (Dadisi.najib@sfpw.org)
5/4/18-5/20/18
Irving Street – (3rd Ave-4th Ave)
Water-line connections and chlorination. Excavation for services between 3rd to 7th avenue for 12″ water main (North side)
Irving Street – (5th Ave-6th Ave)
Southeast parklet sidewalk demo
Southwest parklet installation includes curb, gutter, sidewalk bulb-out
Sewer trench back-fill the week of May 14-18th
Irving Street- (8th Ave-9th Ave)AWSS water-line excavation, installation and backfill for the next month.
Sewer-lining and side-sewer lateral replacement
Demo sidewalk for southwest 8th avenue Parklet and bulb-out corner
Irving Street- (9th Ave-10th Ave)Excavation, installation and backfill the water-line for the next week.
Irving Street (10th Ave-11th Ave)
Replacing side-sewer lateral lines connections to residences and businesses.
Irving Street (15th Ave-18th Ave)
AWSS 20″ (Auxiliary Water Supply System for Emergencies) Installation and backfill trench.
Replace side-latteral sewer lines. Crews will replace only the pipes that are damaged.
Irving Street (17th Ave-18th Ave)
Excavate, install and backfill waterlines for the next 2-weeks
Inner Sunset Streetscape Project – Things to Know:
PROJECT DURATION: 730-days (2-years)
(August 2017 – August 2019)
After years of collaboration between city agencies and community partners, the Inner Sunset Streetscape Improvement Project is underway. This project will improve the N Judah service, beautify your neighborhoods and make your streets more livable, vibrant and sustainable. The project is a partnership between the San Francisco Municipal Transportation Agency (SFMTA) and Public Works (SFPW) and Public Utility Commission (SFPUC).
The work under this contract consists of transit bulb-outs, curb ramps, sewer replacement, landscape improvements, electrical work, water line replacement, and street paving along Irving Street, from Arguello Boulevard to 19th Avenue, 9th Avenue from Irving Street to Judah Street, and 10th Avenue from Irving Street to Judah Street. Additionally, streetscape improvements will occur at the existing transit bulb-outs in Cole Valley at Carl and Cole streets, as well as Carl and Stanyan streets.
PROJECT HIGHLIGHTS
* Sewer repair and replacement
* Water line replacement
* Auxiliary Water Supply System (AWSS) replacement (Emergency Water)
* Traffic Signal upgrades on Irving Street at the 5th and 8th Avenue intersections
* Department of Technology fiber optic installation
* Muni Forward transit bulbouts and pedestrian bulbouts
* Road repaving and ADA curb ramp upgrades
Work hours are Monday-Friday 8AM to 5PM and Saturday-Sunday 8AM-6PM
*(Contractor is allowed to work weekends, however in most case we will not unless it is specially scheduled and neighbors will be notified)
Contractor
Contact information:
Sean Coffey, Project Manager- Mitchell Engineering
24/7 Emergency Phone: 415-740-7828